S-curve modelling in early phases of construction projects

Mladen Radujković, Nives Ostojić-Škomrlj

Abstract

The methodological procedure for forecasting cost distribution over time is given for the project realization phase using cost s-curves for three different types of structures: building, tunnel, and motorway. Three different approaches are used, and their results are correlated and presented in form of mathematical regression expressions and appropriate diagrams. The proposed methodology can be used for cash flow forecasting during all phases of construction projects, specially in the earliest phase in which detailed nformation about the project is scarce.

Keywords
tunnels, motorways, building engineering, construction planning, S-curve, regression models, cost scheduling

HOW TO CITE THIS ARTICLE:

Radujković, M., Ostojić-Škomrlj, N.: S-curve modelling in early phases of construction projects, GRAĐEVINAR, 64 (2012) 8, doi: https://doi.org/10.14256/JCE.714.2012

OR:

Radujković, M., Ostojić-Škomrlj, N. (2012). S-curve modelling in early phases of construction projects, GRAĐEVINAR, 64 (8), doi: https://doi.org/10.14256/JCE.714.2012

LICENCE:

Creative Commons License
This paper is licensed under a Creative Commons Attribution 4.0 International License.
Authors:
3575 Authors 2 RADUJKOVIC WEB
Mladen Radujković
Alma Mater Europaea ECM, Slovenia
Ostojic Skromlj Nives
Nives Ostojić-Škomrlj
University of Split,
Faculty of Civil Engineering, Arch. and Geodesy