Published: Građevinar 71 (2019) 1
Paper type: Subject review
Download article (Croatian): PDF
Download article (English): PDF
Impact of funding on cost-time aspects of public and social buildings
Abstract
The comparison of the traditional (budget-funded) public building procurement model with the public private partnership (non-budget funded) model is presented in the paper. Public service buildings procured based on the traditional model and those procured according to the PPP model are compared in the scope of research involving nine buildings realized in the Republic of Croatia. The results point to greater efficiency of the PPP model in the construction of public service buildings, with regard to both cost and time of construction work.
Keywordstraditional procurement model, PPP, public service buildings, costs, construction time